Northampton Gateway Rail Tunnel 
Scheme details 
Client 
Winvic Construction 
 
JOS Value 
£2.2M 
 
Time 
2021-2022 – 38 weeks 
 
Sectors 
Rail, Industrial 
 
Purpose 
To provide rail access to new rail freight interchange terminal 
Key Data 
180m long rail tunnel, 348 pre-cast concrete beams placed, 11,000m3 concrete poured, 1,600t reinforcement fixed, 1.25m thick walls up to 6m high (EFCO shuttering system). 
JOS Supply 
Labour, Plant (including lifting & concrete pumps) & temporary materials. 
 
 
 
From the summer of 2021 JOS successfully delivered the 180m long rail tunnel. We poured the 6m high, 1.25m wide walls in 20m bays using the EFCO shuttering system. We managed the significant risks of working at height, extensive lifting operations and long concrete installation periods to turn around the shuttering in an efficient sequence with a dedicated SSSTS trained Supervisor to co-ordinate the daily logistics. 
The quality of the product was commended by our client; especially working through poor weather in the winter months. 
 
The scheme was successfully delivered ahead of the Client programme. This was facilitated by the re-design of the original pour sequence where we eliminated several construction joints and extensive temporary works. This also allowed better access for the beam installation and additional programme savings. 
JOS completed the Northampton Gateway Rail tunnel works to the complete satisfaction of the Winvic team in a safe and efficient manner. They were proactive in problem solving for the betterment of the scheme. 
 
Winvic Construction 